Saw Reinforce-ment Metal | 1 | Saw sash lift and lock rail reinforcements | 1 | 1 | 4 | 6 | 12 | 1 | Tammy |
2 | Saw center rail reinforcement | 1 | 1 | 4 | 6 | ||||
Saw Straight Parts | 3 | Saw center rail | 1 | 1 | 2 | 4 | 19 | 1 | Ricky |
4 | Saw sash stops | 1 | 1 | 1 | 3 | ||||
5 | Saw balance covers | 1 | 1 | 2 | 4 | ||||
6 | Saw horizontal glazing bead | 3 | 3 | 2 | 8 | ||||
Process Bead | 7 | Punch vertical glazing bead | 3 | 3 | 2 | 8 | 16 | 1 | Lavonne |
8 | Clip vertical blazing bead | 2 | 2 | 4 | 8 | ||||
Process Center Rail & Reinforcement | 9 | Punch center rail reinforcement | 2 | 2 | 4 | 8 | 62 | 1 | Alex |
10 | End mill center rail | 20 | 7 | 7 | 34 | ||||
11 | Install center rail reinforcement | 4 | 4 | 12 | 20 | ||||
Saw Sash Parts | 12 | Insert weatherstrip into sash lift and lock rails | 2 | 1 | 6 | 9 | 42 | 1 | Charley |
13 | Insert weatherstrip into sash right and left jambs | 2 | 1 | 6 | 9 | ||||
14 | Saw sash lift and lock rails | 3 | 3 | 6 | 12 | ||||
15 | Saw left and right sash jambs | 3 | 3 | 6 | 12 | ||||
Process Sash Parts | 16 | Punch sash lock rail | 4 | 2 | 3 | 9 | 38 | 1 | Kim |
17 | Punch sash lift rail | 4 | 2 | 3 | 9 | ||||
18 | Punch sash lift rail reinforcement | 3 | 2 | 2 | 7 | ||||
19 | Punch sash lock rail reinforcement | 2 | 2 | 2 | 6 | ||||
20 | Insert reinforcements into sash lift and lock rails | 1 | 2 | 4 | 7 | ||||
Saw Frame Parts | 21 | Insert weatherstrip into frame sill | 2 | 2 | 4 | 8 | 32 | 1 | Chris |
22 | Saw frame head and sill | 3 | 3 | 6 | 12 | ||||
23 | Saw frame left and right jambs | 3 | 3 | 6 | 12 | ||||
Process Frame Parts | 24 | Punch frame sill | 3 | 9 | 2 | 14 | 50 | 1 | Terry |
25 | Punch frame head | 1 | 1 | 2 | 4 | ||||
26 | End mill and punch frame jambs | 28 | 2 | 2 | 32 | ||||
Prep Frame Parts | 27 | Install balances in left and right frame jambs | 8 | 2 | 12 | 22 | 60 | 1 | Sabrina |
28 | Install sash stops in left and right frame jambs | 4 | 6 | 0 | 10 | ||||
29 | Install balance shoes in left and right frame jambs | 4 | 4 | 0 | 8 | ||||
30 | Set balances in left and right frame jambs | 3 | 3 | 0 | 6 | ||||
31 | Install balance covers in left and right frame jambs | 8 | 2 | 4 | 14 |